The stages of a residential build, explained
Knowing the order of a build — and what must be finished before the next trade arrives — is the difference between a programme that holds and one that drifts.
1. Site establishment and setout
Access, safety, services and laydown are sorted, then the building is set out against the survey and the plans. Setout errors here get more expensive at every stage that follows, so it is worth the time to check twice.
2. Foundations and floor
Foundation type follows the geotech and engineering design — slab, piles or a timber floor system. This is one of the stages where Canterbury ground conditions can meaningfully change both cost and duration.
3. Framing and structure
Wall framing, midfloors, structural beams and steel go up, followed by roof framing or truss install. Bracing and fixings must match the engineer's details because this is what gets inspected and what the rest of the build hangs off.
4. Roof, wrap and cavity
Roof substrate and roofing go on to get the building closed in, then building wrap and cavity battens. Getting weathertight promptly protects the timber and lets interior work start.
5. Windows and exterior doors
Joinery is installed and flashed. Delivery timing on joinery is one of the most common causes of programme slip, so it needs to be tracked well before the frames are up.
6. Services rough-in and pre-line
Plumbing, electrical and any mechanical services are roughed in, insulation goes in, and the pre-line inspection happens. Everything hidden behind the linings has to be right at this point.
7. Linings, stopping and painting
Interior linings are fixed, stopped and painted. The quality of the framing shows up here — out-of-plumb or twisted framing costs the stoppers and painters time.
8. Fit-off
Doors, hardware, skirtings, architraves, wardrobes, vanities and joinery are installed, then plumbing and electrical fit-off. This is the stage the client actually inspects, so consistency matters more than speed.
9. Final inspections, defects and handover
Council final inspection, code compliance, defect list closeout and handover. A short defect list is the clearest evidence that the earlier stages were run properly.
Where programmes usually slip
- —Setout or documentation issues discovered after framing has started.
- —Joinery and material lead times not tracked early enough.
- —Stages called 'finished' when they are 90 per cent done, blocking the next trade.
- —Failed inspections that require a return visit.
- —Weather with no contingency built into the programme.
